分享这篇文章

在Kaleva, 坦佩雷, an extensive transformation is underway as the iconic Hippostalo building from the 1970s and 1980s is set to be replaced, marking the largest project in the history of the 坦佩雷 Student Housing Foundation 加强.

加强河马 is a new timber-based student housing block accommodating over 800 students in approximately 650 flats. 加强河马 will have a total floor area of approximately 35,000 square meters and will be built mainly of CLT modular elements as a single building. 除了居住空间, 大楼还将包括会议室, 办公室, 还有超市. Our experts carried out fire dynamic calculations, 耐火试验, 风险分析 of the CLT firewall planned for the site, as well as fire and evacuation simulations due to the exceedingly prescriptively allowed size of the fire compartment and the number of people in the building. The design of the project was also closely followed during the implementation phase, and expert supervision was carried out on-site during the works, as required by the building control authorities.

规定要求35,000 square meters of floor area to have two non-combustible firewall structures to limit maximum potential fire spread in the large mass timber building. 然而, the pouring of the concrete firewall proved to be a challenge, as it did not fit into the schedule of the prefab construction. 然而, there was no justification for not building the firewalls, and the challenge was addressed through performance-based design using fire severity calculations, 耐火试验, 风险分析.

基于性能的设计, a double-wall structure was designed for 加强河马 that was proved to meet or exceed the performance of the prescriptive non-combustible firewall. The wall structure was subjected to the necessary fire tests to demonstrate its resistance to the required impact loads. The tests were also used to assess the time of onset of charring, 哪一个是验收标准.

加强河马的构建方法, 基于CLT模块化元素, required an exceptional firewall solution due to the construction schedule, as it was not desirable to build firewalls several tens of meters high using concrete. The double-wall structure designed and tested meets the fire resistance of a firewall built out of non-combustible material, but now the firewall structure can be completed off-site at the modular factory, 施工可以按计划进行. These innovative solutions contributed to the development of the vibrant urban student village of the future in 坦佩雷's Kaleva.

项目详细信息

客户端

加强

项目位置

坦佩雷,芬兰

预计工程费用

130,000,000 €

项目的规模

最大8层,35000平方米

时间轴

2025

彩宝网
商业
教育

有特色的专家

Aleksi Ojala

欧洲Mass Timber服务线负责人

坦佩雷——芬兰

理学硕士,土木工程, FISE消防安全设计师(PV级)

查看详细信息

詹森·休斯报道更多内容